Tada! The footers are complete. Notice the 5 small footers in the foreground - those are for the back deck.
Then May 13, 2010 rolls around and the boys have some nice weather to put in the forms on top of the footers for the stem walls.
They did it despite the weather in Mayuary. The posts you see in the foreground are sonotubes that will also be filled with concrete and then will be underground to support the posts for the back deck.
Tomorrow... weather permitting... Ben and the boys will fill the stem walls with concrete and let it set over the weekend. The first floor height is the height of the top of the white walls you see.
No comments:
Post a Comment